CONSTRUCTION PROGRESS

There has been good progress made on the West Annex this past week.  I hope that you can get some perspective of the tremendous number of pipes and conduit that is being buried under the pad.  There are pipes sticking up everywhere for all the sinks in the FACS lab, science lab and classroom area of Ag. Ed.  If you look closely in some of the pictures you will see they are forming up the sides for the pad.
 
Wednesday the 23rd is going to be a very big day in the construction phase. They have reserved a cement pumper truck and they will have 25 cement trucks delivering all the cement needed within a three hour time frame.  There will be a double crew on hand to work the cement. If you have time to drop by, next Wednesday would be a very good day to see a lot of action here.
 
Foundation work on the storm shelter should start sometime next week.  I hope you can come out next Wednesday to take pictures and report!